Pool Construction
Lake Guntersville Pool has been making backyard dreams come true since 2003. We have become one of the top builders in the region, by using only the most innovative, quality and eye-catching products in the industry.
Steps of the Building Process
The typical process starts out with the planning and designing of your dream pool. We start with an initial consultation discussing options and viewing the site of the pool. Once a location is selected we will custom design your pool to achieve the desired result based on your individual wants, space, and budget.
Once a commitment to the project is made we prepare to start at a specified time frame. With each project being different, some can take 3-6 weeks to complete. Each homeowner works directly with the owners of the company along with their highly trained and experienced staff.
Typical Vinyl Liner Pool Construction
Day 1
Excavation of pool per pool specifications.
Day 2 - 3
We set the pool walls, all steps, ledges, and benches, and pour footer.
Day 4 - 5
We tackle the plumbing of the pool, set up the filtering system, and backfill over dig along with the 1st round of grading.
Day 6
We prepare the pool bottom, grout the pool bottom, and install the pool liner. Then we start filling the pool.
Once the pool liner is installed, we will return in 24 hours to cut out all of the openings needed for filtration and prepare the pool for electrical inspections. An electrician will start wiring the pool so that we can get the system running to maintain the water. Once the electrical inspection is completed we can proceed to prep for concrete and completion of the project. When the project is completed we will meet with the homeowner for a complete walk thru while teaching and explaining how to maintain their pool.
This is only a time line guide. We try to adhere to the strictest of time lines but weather, supplies, or other obstacles may hinder completion dates.